OPERATION OF DEHUMDIFIER

  • PROCEDURE:
  • STARTING PROCEDURE :
  • Ensure that AHU runs before Switching ON Dehumidifier.
  • Operate the AHU as per the SOP.
  • Ensure that Process air & Reactivation air Dampers of the dehumidifier are in open condition.
  • Ensure the Inlet Valve and Outlet Valve of Steam Coil are in open Condition, and Bypass valve is in closed position.
  • Ensure that Steam Pressure is of 6±1kg/cm2.Switch ON the main MCB.
  • Select the Auto mode to operate automatically and Manual mode to operate the system in manual mode.
  • Ensure the set parameters of the dehumidifier shall yield desired Rh.
  • Switch ON the ON/OFF switch.
  • Ensure the set parameters of dehumidifier Safety thermostat should be 160°C, cool down thermostat should be 70°C and operation thermostat should be in the range of 100°C -140°C.If Dehumidifier runs continuously run, put ‘RC’, in ON time of log sheet.
  •  STOPPING PROCEDURE:
  • Switch OFF the ON/OFF switch.
  • Switch OFF the MCB.
  • Close the process air and reactivate air dampers after switching off the dehumidifier.
  • If the Dehumidifier runs continuously, put ‘RC’ in OFF time Column of log sheet.
  • Whenever performed preventive maintenance activity and filter cleaning activity the same shall be recorded in the remarks column of Annexure-I.
  • REFERENCES:
  •   Not Applicable
  • ANNEXURES: 
ANNEXURE No.TITLE OF ANNEXURE
Annexure-IDehumidifier Log Sheet
  • ENCLOSURES: SOP Training Record.
  • DISTRIBUTION:
  • Controlled Copy No. 01                     Head Quality Assurance
  • Controlled Copy No. 02                 Head-Engineering
  • Master Copy                           Quality Assurance Department
  • ABBREVIATIONS:
  • SOP     :      Standard Operating Procedure
  • AHU    :      Air Handling Unit.
  • MCB      :    Main Circuit Breaker
  • REVISION HISTORY:
  •    CHANGE HISTORY LOG
Revision No.Details of ChangesReason for ChangeEffective Date
00New SOPNot ApplicableTo be written manual

Annexure-I
DEHUMIDIFIER LOG SHEET

DEHUMIDIFIER LOG SHEET
Share this article
Shareable URL
Prev Post

CALIBRATION OF ALLIANCE HPLC WITH EMPOWER SOFTWARE FOR PDA AND UV DETECTOR

Next Post

OPERATION OF COOLING TOWER

Leave a Reply

Your email address will not be published. Required fields are marked *

Read next

Discover more from PharmaGuideHub

Subscribe now to keep reading and get access to the full archive.

Continue reading