- PROCEDURE:
- STARTING PROCEDURE :
- Ensure that AHU runs before Switching ON Dehumidifier.
- Operate the AHU as per the SOP.
- Ensure that Process air & Reactivation air Dampers of the dehumidifier are in open condition.
- Ensure the Inlet Valve and Outlet Valve of Steam Coil are in open Condition, and Bypass valve is in closed position.
- Ensure that Steam Pressure is of 6±1kg/cm2.Switch ON the main MCB.
- Select the Auto mode to operate automatically and Manual mode to operate the system in manual mode.
- Ensure the set parameters of the dehumidifier shall yield desired Rh.
- Switch ON the ON/OFF switch.
- Ensure the set parameters of dehumidifier Safety thermostat should be 160°C, cool down thermostat should be 70°C and operation thermostat should be in the range of 100°C -140°C.If Dehumidifier runs continuously run, put ‘RC’, in ON time of log sheet.
- STOPPING PROCEDURE:
- Switch OFF the ON/OFF switch.
- Switch OFF the MCB.
- Close the process air and reactivate air dampers after switching off the dehumidifier.
- If the Dehumidifier runs continuously, put ‘RC’ in OFF time Column of log sheet.
- Whenever performed preventive maintenance activity and filter cleaning activity the same shall be recorded in the remarks column of Annexure-I.
- REFERENCES:
- Not Applicable
- ANNEXURES:
ANNEXURE No. | TITLE OF ANNEXURE |
Annexure-I | Dehumidifier Log Sheet |
- ENCLOSURES: SOP Training Record.
- DISTRIBUTION:
- Controlled Copy No. 01 Head Quality Assurance
- Controlled Copy No. 02 Head-Engineering
- Master Copy Quality Assurance Department
- ABBREVIATIONS:
- SOP : Standard Operating Procedure
- AHU : Air Handling Unit.
- MCB : Main Circuit Breaker
- REVISION HISTORY:
- CHANGE HISTORY LOG
Revision No. | Details of Changes | Reason for Change | Effective Date |
00 | New SOP | Not Applicable | To be written manual |
Annexure-I
DEHUMIDIFIER LOG SHEET