- OBJECTIVE:
- To lay down the procedure for operation of Milli-Q Water purification System.
- SCOPE:
This SOP is applicable to the procedure for Operation of Milli-Q Water purification System at {Company Name} {Location}.
- RESPONSIBILITY:
- Officer/Executive/Designee Quality Control – Shall be responsible for operation as per SOP.
- Head/Designee Quality Control – Shall be responsible for ensuring compliance as per SOP.
- ACCOUNTABILITY:
QA Head shall be Accountable for implementation of SOP.
- PROCEDURE:
- For General Cleaning:
- Ensure that the power supply to the instrument is switched ‘OFF’ before cleaning.
- Clean the instrument with a clean dry cloth every day. Use clean cloth dipped in soap solution if necessary.
- Care should be taken to remove the water with a dry cloth.
- Operating Procedure:
- Milli-Q water: This is ultrapure water that has been produced using a Millipore Milli-Q water purification system.
- Milli-Q water purification systems: These are systems that are used to produce Milli-Q water.
- Switch on the main power switch provided on the backside of the instrument.
- Move the “Point of use” trigger in a click way till the green bulb glowing starts to initiate the water purifying process.
- The green bulb starts glowing.
- When the bulb is glowing, conductivity or resistivity of waters displays.
- Then further move the “Point of use” trigger to start the dispensing of water.
- After collecting the water click on the “Point of use” trigger to its original position.
- Press the “OPERATE / STAND BY” button for at least 2 seconds to go to “STAND BY” mode.
- The water resistivity shall be verified twice in a day.
- Instrument shall not be used if the output water resistivity is less than 18.2 MW. cm.
- The Cartridges shall be replaced as below given and the details of the change shall be entered in Annexure-II.
- Quantum Ultra-pure Cartridge: As and when required.
- Q-Guard Purification pack: As and when required.
- Mill pack 40: When the flow rate is too low (<0.5 Liters per Minute)
- For General Cleaning:
- REFERENCES:
Not Applicable
- ANNEXURES:
ANNEXURE NO. | TITLE OF ANNEXURE |
Annexure-I | Daily Monitoring Record |
Annexure-II | Cartridge Replacement record |
ENCLOSURES: SOP Training Record.
- DISTRIBUTION:
- Controlled Copy No. 01 : Head Quality Assurance
- Controlled Copy No. 02 : Head Quality Control
- Master Copy : Quality Assurance Department
- ABBREVIATIONS:
No. | : | Number |
SOP | : | Standard Operating Procedure |
QC | : | Quality Control |
- REVISION HISTORY:
CHANGE HISTORY LOG
Revision No. | Details of Changes | Reason for Change | Effective Date |
00 | New SOP | Not Applicable | To Be Written Manual |
Annexure-I
Daily Monitoring Record