- PROCEDURE:
- When EB power fails, immediately start the DG set.
- Check and ensure the Voltage, RPM, Frequency & Oil pressure.
- Close the DG control panel ACB.
- Close the DG incomer ACB in the power control center.
- Concerned engineering personnel has to switch on the AHU’s, DHU’s, utility equipments and remaining loads.
- When EB power resumes check and ensure the 3 Phase voltages should be in-between 415 – 420 Volts.
- Intimate to the production in- charge for soft shut down of all the loads.
- Open the DG incomer ACB in the PCC panel.
- Close the EB incomer ACB in the PCC panel.
- Open DG control panel ACB.
- Stop the DG set after 5 minutes idle running.
- Above mentioned EB power to DG power or DG power to EB power changeover procedure should be complete within 02 minutes only.
- REFERENCES:
- Not Applicable
- ANNEXURES:
- Not Applicable
- ENCLOSURES: SOP Training Record.
- DISTRIBUTION:
- Controlled Copy No. 01 Head Quality Assurance
- Controlled Copy No. 02 Head-Engineering
- Master Copy Quality Assurance Department
- ABBREVIATIONS:
- DG Set : Diesel Generator Set
- ACB : Air circuit breaker
- PCC : Power control center
- RPM : Revolutions per minute
- EB : Electricity board
- AHU : Air handling unit
- DHU : De-humidifier unit
- SOP : Standard Operating Procedure
- REVISION HISTORY:
- CHANGE HISTORY LOG
Revision No. | Details of Changes | Reason for Change | Effective Date |
00 | New SOP | Not Applicable | To be written manual |