OPERATING PROCEDURE OF HOT WATER GENERATOR

  • PROCEDURE:
  • Checks to be carried out before starting the Hot water generation system.
  • Check the Main power supply is available.
  • Check the water level in the makeup tank and if needed fill up to the level.
  • Check and ensure that the hot water inlet and outlet valves are in open condition.
  • Check the steam line outlet valve should be in opened condition in Pressure Reducing Station (PRDS) and ensure the steam pressure NMT 3.0 Kg/Cm2.
  • Ensure the availability of compressed air pressure NMT 4.0 Kg/Cm2
  • STARTING PROCEDURE:
  • Switch ‘ON’ the control supply of the PID controller.
  • Switch ‘ON’ hot water circulation pump.
  • Set the temperature on the PID controller 50°C, + 10°C by using the UP and DOWN arrow keys on PID controller.
  • Open the steam line inlet valve.
  • When temperature reaches set temperature in the hot water return line PID cutoff the steam supply. 
  • When the temperature reaches below set temperature in the hot Water return line PID SWITCH ON the steam supply.
  • SAFETY PRECAUTIONS
  • Don’t open the PRV inlet steam valve while the water circulation pumps in ‘OFF’ position.
  • Don’t carry any maintenance works while the system is running, or steam and hot water pressurized in the pipelines.
  • STOPPING PROCEDURE
  • Close the PRV inlet steam valve.
  • Close the compressed air valve.
  • Switch ‘OFF’ the control supply to the PID controller.
  • After the water temperature comes 40 º C switches OFF the hot water recirculation Pump.
  • Record the parameters every two hours as per Annexure-I.
  • REFERENCES:
  •   Not Applicable
  • ANNEXURES: 
  ANNEXURE No.TITLE OF ANNEXURE
Annexure-IHot Water Generation log sheet
  • ENCLOSURES: SOP Training Record.
  • DISTRIBUTION:
  • Controlled Copy No. 01                     Head Quality Assurance
  • Controlled Copy No. 02                 Head-Engineering
  • Master Copy                           Quality Assurance Department
  • ABBREVIATIONS:
  • Kg/Cm2     :        Kilogram / Square Centimeter.
  • PRV           :        Pressure reducing valve.
  • NMT         :        Not More Than.
  • NLT         :        Not Less Than
  • REVISION HISTORY:
  •  CHANGE HISTORY LOG

Annexure-I
HOT WATER GENERATION LOG SHEET

 HOT WATER GENERATION LOG SHEET

Share this article
Shareable URL
Prev Post

OPERATION OF ALLIANCE HPLC WITH EMPOWER SOFTWARE

Next Post

OPERATION OF ELECTRICALLY OPERATED AUTOMATIC PRESS

Leave a Reply

Your email address will not be published. Required fields are marked *

Read next

Discover more from PharmaGuideHub

Subscribe now to keep reading and get access to the full archive.

Continue reading