OPERATING PROCEDURE OF THE 2000 KVA TRANSFORMER

  • OBJECTIVE:

To lay down a procedure for operation of 2000 KVA Transformer.

  • SCOPE:

This SOP is applicable for operation of 2000 KVA Transformer at {Company Name} {Company Location}.

  • RESPONSIBILITY:
  • Technical Assistant – Engineering is responsible to operate the equipment as per the SOP.
  • Head Engineering / In charge – is responsible to ensure the compliance as per the SOP.
  • ACCOUNTABILITY:

Engineering Head

Head Quality Assurance

  • PROCEDURE:
  • Ensure the HT outgoing VCB should be in open condition at the HT panel.
  • Check and ensure the oil level in the Transformer and OLTC up to the mark.
  • Ensure all radiator valves are in open position.
  • Check and ensure for no oil leakages at all the gaskets.
  • Check and ensure the silica gel colour in the breather for sky blue and oil level in the bottom cup up to the mark.
  • Check and ensure for no tools laying on the transformer.
  • Check and ensure transformer for proper neutral & body earthing.
  • Check and reset if any alarms in the RTCC panel.
  • Release the emergency push button at OLTC panel.
  • Close the HT outgoing VCB at the HT panel and observe the LT voltages at the PCC panel.
  • REFERENCES:

  Not Applicable

  • ANNEXURES: 

  Not Applicable

ENCLOSURES: SOP Training Record.

  • DISTRIBUTION:
  • Controlled Copy No. 01                     Head Quality Assurance
  • Controlled Copy No. 02                 Head-Engineering
  • Master Copy                           Quality Assurance Department
  • ABBREVIATIONS:

OLTC      :      On Load Tap Changer

RTCC      :       Remote Tap changer cubical

VCB   :      Vacuum Circuit Breaker

HT           :       High Tension

LT           :       Low Tension

PCC   :      Power Control Centre

KVA        :       Kilo Volt Ampere

  • REVISION HISTORY:
                                                             CHANGE HISTORY LOG
Revision No.Details of Changes Reason for ChangeEffective Date
00New SOPNot ApplicableTo be written manual
Share this article
Shareable URL
Prev Post

PASSIVATION OF STORAGE & DISTRIBUTION PURIFIED WATER SYSTEM

Next Post

PROCEDURE FOR OPERATION OF UN-INTERRUPTIBLE POWER SUPPLY – 40 KVA

Leave a Reply

Your email address will not be published. Required fields are marked *

Read next

AHU PARAMETER MONITORING

To lay down a procedure for AHU Parameter monitoring. This SOP is applicable for AHU Parameter monitoring at…
AHU PARAMETER MONITORING

Discover more from PharmaGuideHub

Subscribe now to keep reading and get access to the full archive.

Continue reading