OPERATING PROCEDURE OF WATER COOLED CHILLER

  • OBJECTIVE:

To lay down procedure for the operation of Water Cooled Chiller.

  • SCOPE:

This SOP is applicable for the operation of Water Cooled Chiller at {Company Name} {Company Location}.

  • RESPONSIBILITY:
  • Technical Assistant – Engineering is responsible for operating the equipment as per the SOP.
  • HOD/Executive – Engineering is ensure the compliance as per SOP.
  • ACCOUNTABILITY:

Engineering Head

Head Quality Assurance

  • PROCEDURE:
  • Precautions:
  • Check the level of soft water in the overhead tank, it should be 3/4th or above, if needed fill with soft water.
  • Check the cooling tower water level which should be above half level.
  • Ensure that the suction and delivery valves of chilled water circulation pumps and cooling water pump are open.
  • Ensure cooling towers and chilled water tank make-up water line valves are in open position.
  • Ensure condenser and evaporator in & outlet lines valves are in open position
  • Ensure power supply to panel.Check and ensure the oil level as per the mark given on the view glass.
  • PRE START UP
  • Switch on the input power supply of the chiller.
  • Start the cooling water pumps and related cooling tower fans.
  • Start the chilled water circulation pumps one by one based on plant load.
  • Check and ensure no air lock occurred in the chilled water distribution loop
  • STARTING PROCEDURE
  • Before starting the unit, ensure that all AHU’s are in OFF condition, but valves should be in OPEN condition.
  • Any set points which are desired to be changed may be programmed.
  • All Control Center set points should be programmed before the chiller is started.
  • Maintain the required inlet chilled water pressure. If the flow rate is less than minimum rated flow (3 kg/cm2), the flow switch will be tripped off the system.
  • After getting the flow press and then touch local ON button in MMI and then start the chiller.
  • When the chilled water temperature reaches 6.5ºC, and then starts the AHU’s.
  • Set chilled water outlet temperaure NLT 5℃
  • Every two hours note down the readings as per enclosed Annexure-I.
  • STOPPING PROCEDURE:
  • Press the and then touch STOP button and then stop the chiller.After 1 to 2 minutes the system will be shut down completely.Switch off the chiller pumps and cooling tower pumps.
  • Switch off the cooling tower fans.

    Click the link to download word file copy of this document:
    https://pharmaguidehub.com/product/operating-procedure-of-water-cooled-chiller/

    • REFERENCES:

      Not Applicable

    • ANNEXURES: 
      ANNEXURE No.TITLE OF ANNEXURE
    Annexure-IWater Cooled Chiller Log Sheet

    ENCLOSURES: SOP Training Record.

    • DISTRIBUTION:
    • Controlled Copy No. 01                     Head Quality Assurance
    • Controlled Copy No. 02                 Head-Engineering
    • Master Copy                           Quality Assurance Department
    • ABBREVIATIONS:

    AHU    :    Air Handling Units.

    MMI     :     Man, Machine Interface

    • REVISION HISTORY:
                                                                 CHANGE HISTORY LOG
    Revision No.Details of Changes Reason for ChangeEffective Date
    00New SOPNot ApplicableTo be written manual

    ANNEXURE-I
    WATER COOLED CHILLER LOG SHEET

    WATER COOLED CHILLER LOG SHEET

    Click the link to download word file copy of this document:
    https://pharmaguidehub.com/product/operating-procedure-of-water-cooled-chiller/

    Share this article
    Shareable URL
    Prev Post

    OPERATION OF AIR COMPRESSOR AND AIR DRYER

    Next Post

    OPERATING PROCEDURE OF DG SET

    Leave a Reply

    Your email address will not be published. Required fields are marked *

    Read next

    Discover more from PharmaGuideHub

    Subscribe now to keep reading and get access to the full archive.

    Continue reading